Commercial impracticability

What Is Commercial Impracticability?

Commercial impracticability is a legal defense in contract law that allows a party to be excused from performing their contractual obligations when unforeseen circumstances make performance excessively difficult or expensive. This doctrine falls under the broader category of excuses for non-performance in contract law, often invoked when adhering to the original terms of a contract would result in an unreasonable burden not contemplated by the parties at the time of agreement. While performance remains physically possible, commercial impracticability argues that the drastically altered circumstances render the performance fundamentally different from what was originally intended54. The Uniform Commercial Code (UCC) and the Restatement (Second) of Contracts are key legal frameworks that address commercial impracticability53.

History and Origin

The doctrine of commercial impracticability evolved from earlier, stricter interpretations of contract enforceability. Historically, English common law adhered to the principle of "pacta sunt servanda," meaning agreements must be kept, even in the face of hardship. The case of Paradine v. Jane (1647) is often cited for this rule of absolute liability, where courts generally refused to excuse a party even if an event occurred after contract formation that affected their ability to perform51, 52.

However, this strict approach began to soften in the 19th century with cases like Taylor v. Caldwell (1863), which introduced the concept of impossibility as a defense, primarily when the subject matter of a contract was destroyed50. The concept further broadened with the introduction of "impracticability," recognizing that performance could be excused not only when literally impossible but also when it could "only be done at an excessive and unreasonable cost"49. This shift acknowledged that unforeseen external factors, such as natural disasters or significant economic upheavals, could impact contractual performance48.

In the United States, the codification of contract principles in the Uniform Commercial Code (UCC) in the 20th century, specifically Section 2-615, and the Restatement (Second) of Contracts (Section 261) formalized the doctrine of commercial impracticability, providing a framework for its application in modern contract law46, 47.

Key Takeaways

  • Commercial impracticability is a legal defense used to excuse contractual performance when unforeseen circumstances make it extremely difficult or unreasonably expensive.45
  • The doctrine applies when the non-occurrence of an event was a basic assumption of the contract, and the event was not caused by the fault of the party seeking excuse.43, 44
  • It is recognized under the Uniform Commercial Code (UCC § 2-615) for contracts involving the sale of goods and the Restatement (Second) of Contracts for other types of agreements.
    41, 42* Mere market shifts or financial inability generally do not constitute commercial impracticability, as these are considered foreseeable business risks.
    40* Courts evaluate whether the unforeseen event was beyond the control of the party seeking excuse and whether the risk was assumed within the contract.
    39

Interpreting Commercial Impracticability

Interpreting commercial impracticability involves a multi-faceted analysis by courts to determine if the conditions for excuse are met. The core elements typically require proving that:

  1. An unforeseen event occurred, the non-occurrence of which was a basic assumption upon which the contract was made.37, 38 This means the parties entered the agreement assuming this specific event would not happen.
  2. The occurrence of this event made performance "impracticable," meaning it would involve extreme and unreasonable difficulty, expense, injury, or loss to one of the parties.36 The burden must be substantial and beyond what could have been reasonably anticipated or priced into the original agreement.
  3. The party seeking to be excused was not at fault for the unforeseen event and did not assume the risk of the event in the contract.34, 35 This often requires demonstrating that the party acted in good faith in attempting to fulfill their obligations despite the changed circumstances.33

Courts will scrutinize the contract terms to see if specific provisions, such as a force majeure clause, already address the allocation of such risks.31, 32 The concept of risk allocation is central; if the parties explicitly or implicitly allocated the risk of the event, the defense of commercial impracticability may not apply.

Hypothetical Example

Consider a scenario involving "GreenBuild Co.," a construction firm that contracts to build a sustainable commercial office building using a specific, newly developed eco-friendly concrete. The contract includes a fixed price for materials, with the understanding that the concrete supplier, "EcoMix Inc.," will deliver the material from its sole plant, located in a region prone to seasonal wildfires but which had not experienced a major fire in decades.

Mid-project, an unprecedented series of wildfires, exacerbated by unusual drought conditions, devastates the region, completely destroying EcoMix Inc.'s plant and disrupting all local transportation infrastructure for months. While GreenBuild Co. could theoretically source similar concrete from a plant across the country, the cost of transportation and the material itself would increase the total project cost by 60%, pushing GreenBuild Co. into severe financial distress and making the project unprofitable.

In this case, GreenBuild Co. might invoke commercial impracticability. The destruction of the local concrete plant due to unforeseen and severe wildfires was a contingency whose non-occurrence was a basic assumption of the contract. Acquiring the material at a significantly higher cost would impose an extreme and unreasonable burden, fundamentally altering the nature of the contractual obligations and falling outside the scope of normal business risks or anticipated supply chain disruptions.

Practical Applications

Commercial impracticability primarily finds application in situations where unexpected events disrupt contractual performance, particularly in commercial transactions. It is frequently invoked in:

  • Supply Chain Disruptions: When natural disasters, geopolitical events, or widespread crises severely impact the availability or cost of raw materials or components, making original contracts unfeasible.
  • Construction Contracts: Projects can face unforeseen geological issues, material shortages, or regulatory changes that drastically increase the cost or difficulty of completion.
  • Sales of Goods: Under the Uniform Commercial Code (UCC) Section 2-615, a seller may be excused from delivery if performance is made impracticable by unforeseen contingencies, provided they act in good faith and notify the buyer.30 For instance, a supplier facing a sudden and significant increase in raw material costs due to an unforeseen event might invoke commercial impracticability rather than face a breach of contract claim.29 The UCC requires that the seller allocate remaining capacity fairly among customers and notify them of any delays or non-delivery [UCC § 2-615].
  • Government Contracts: Specific provisions often exist in government contracts that address unforeseen circumstances impacting performance.

Parties often try to address such risks through explicit force majeure clauses in their contracts, but when such clauses are absent or don't cover the specific event, commercial impracticability can serve as a legal recourse. 27, 28This allows for a potential renegotiation of terms or discharge of the contract, rather than forcing a party into ruinous performance.
26

Limitations and Criticisms

Despite its role in providing flexibility in contract law, the doctrine of commercial impracticability has significant limitations and is often applied narrowly by courts. A primary criticism is the difficulty in defining what constitutes "extreme and unreasonable difficulty or expense". Courts are generally reluctant to reallocate risk allocation simply because a contract has become less profitable or even unprofitable.
25
Key limitations include:

  • Foreseeability: The event making performance impracticable must have been unforeseeable at the time the contract was made. If the risk was known or reasonably foreseeable, the defense typically fails.
  • Assumption of Risk: If the contract language indicates that a party assumed the risk of the particular event, they cannot claim commercial impracticability.
    24* Mere Market Shifts or Financial Inability: A significant increase in costs, a decrease in demand, or a party's financial distress are usually not sufficient grounds for commercial impracticability. Courts generally view these as normal business risks that parties assume when entering into agreements. 23For example, "mere market shifts or financial inability do not usually effect discharge".
    22* Good Faith: The party seeking to invoke commercial impracticability must demonstrate that they have acted in good faith and have exhausted reasonable alternatives to performance, including attempts at negotiation.
    20, 21
    The application of commercial impracticability aims to balance the sanctity of contracts with the need for fairness in unforeseen circumstances. However, it does not guarantee an escape from a bad deal or provide automatic remedies for adverse economic conditions.

Commercial Impracticability vs. Impossibility

While often discussed together and sometimes used interchangeably by courts, commercial impracticability and impossibility are distinct legal doctrines excusing contractual performance.

FeatureCommercial ImpracticabilityImpossibility
Performance StatusPerformance is still physically possible but has become unreasonably difficult, expensive, or burdensome due to unforeseen events.19 Performance is rendered literally or objectively impossible (e.g., subject matter destroyed, party essential to performance dies). 18
Degree of DifficultyRequires extreme and unreasonable difficulty, expense, injury, or loss. 17Requires performance to be physically or legally unable to be done. 15, 16
ForeseeabilityEvent must be unforeseen and its non-occurrence a basic assumption of the contract. 14Event typically unforeseen, making performance objectively impossible.
UCC & RestatementExplicitly recognized in UCC § 2-615 and Restatement (Second) of Contracts § 261. 12, 13Rooted in common law; while related, it is not explicitly codified in the UCC in the same way as impracticability. 11

The key distinction lies in the feasibility of performance. Impossibility means "it cannot be done," while commercial impracticability means "it can only be done at an excessive and unreasonable cost or difficulty".

#9, 10# FAQs

What does "impracticability" mean in a contract?

In a contract, "impracticability" means that performing the agreed-upon duties has become extremely difficult, expensive, or burdensome for one party due to an unforeseen event that was not a basic assumption of the contract. It does not mean performance is literally impossible, but rather that it would be fundamentally unfair to require it under the changed circumstances.

What is the difference between commercial impracticability and force majeure?

Commercial impracticability is a legal doctrine that may excuse performance when unforeseen events make it extremely difficult. Force majeure, on the other hand, is a specific clause written into a contract that defines which events (like natural disasters, wars, or pandemics) will excuse performance. If7, 8 a contract has a force majeure clause, it will generally govern; if not, or if the event isn't covered, commercial impracticability might be invoked as a common law defense.

Can a rise in cost lead to commercial impracticability?

Generally, a mere rise in cost, even a substantial one, is not enough to claim commercial impracticability. Courts consider market fluctuations and financial difficulties to be normal business risks that parties assume when entering a contract. Fo6r commercial impracticability to apply due to increased cost, the rise must be caused by an unforeseen contingency that fundamentally alters the nature of the performance, making it radically different from what was contemplated.

Is commercial impracticability a valid defense in all contracts?

Commercial impracticability is a recognized legal defense in many jurisdictions, particularly in the United States under the Uniform Commercial Code (for sales of goods) and the Restatement (Second) of Contracts (for other contracts). Ho4, 5wever, its application depends heavily on the specific facts of the case, the terms of the contract, and the governing law. It is typically a difficult defense to prove.

What happens if a contract is deemed commercially impracticable?

If a court determines that a contract is commercially impracticable, the party whose performance is affected may be discharged from their contractual obligations. Th3e court may also allow for partial performance or order restitution for benefits conferred before the impracticability arose. Th1, 2e outcome aims to provide a fair resolution given the unforeseen circumstances.